Fit-out approvals in Dubai: who approves what (2026)

The short answer

A Dubai fit-out is approved in this order: landlord consent, then the permit from the authority for the area (Dubai Municipality on the mainland, the DDA, Trakhees or the free zone), then Civil Defence for fire systems, DEWA if the power load changes, and finally a completion certificate. The contractor or consultant submits, not the tenant. Mainland and DDA units of 100 sq m or less, and mall units, need no authority permit.

OrderLandlord, then authority
DDA Fit-Out Permit2 working days
No DM or DDA permit up to100 sq m

The data behind this guide: our open dataset fit-out approvals by jurisdiction in Dubai lists, for 11 jurisdictions, the approving body, the permit as the body names it, who submits, the Civil Defence step, and the published timing and fee, with a source for every cell and a CSV download.

What is the order of fit-out approvals in Dubai?

Landlord first, then the authority for the area, then Civil Defence and DEWA where the scope needs them, then completion.

Office fit-out approvals in Dubai, in order 1. Landlord or building owner consent. 2. Permit from the authority for the area. 3. Civil Defence approval. 4. DEWA, if power or water changes. 5. Inspection and completion certificate 1 Landlord or building owner consent NOC or written consent; free zone landlordsapply their own fit-out manual Tenant asks; landlord issues 2 Permit from the authority for the area Dubai Municipality, DDA, Trakhees or the freezone process Approved contractor or consultant submits 3 Civil Defence approval Fire alarm, sprinklers and fire safety, wherethe body requires it Contractor 4 DEWA, if power or water changes Load increase, new meters or a fit-outconnection Contractor or consultant 5 Inspection and completion certificate Then the unit can open for business Contractor applies; authority or landlordissues
  1. Landlord or building owner consent: NOC or written consent; free zone landlords apply their own fit-out manual (Tenant asks; landlord issues)
  2. Permit from the authority for the area: Dubai Municipality, DDA, Trakhees or the free zone process (Approved contractor or consultant submits)
  3. Civil Defence approval: Fire alarm, sprinklers and fire safety, where the body requires it (Contractor)
  4. DEWA, if power or water changes: Load increase, new meters or a fit-out connection (Contractor or consultant)
  5. Inspection and completion certificate: Then the unit can open for business (Contractor applies; authority or landlord issues)
The general sequence. Some free zones run every step through the landlord, and small or mall units can be exempt from the authority permit. Sources: Dubai Municipality, Administrative Resolution 85 of 2019, DDA service pages, Jafza and Dubai South fit-out manuals.
  1. Landlord consent. Every route starts here. Dubai Municipality needs the written consent of the unit's owner; the DDA asks for an NOC; DMCC companies request an NOC to Concordia on the DMCC member portal; DIFC tenants follow the Fit-Out Manual referred to in their lease, issued on the DIFC Client Portal.
  2. Authority permit. On the mainland, a contractor on Dubai Municipality's approved list gets an instant self permit for decoration works in units over 100 sq m. In DDA zones the contractor applies for the Fit-Out Permit. In Trakhees areas any modification or fit-out of a completed facility needs a Modification Permit. JAFZA adds a Modification NOC before the Trakhees permit.
  3. Civil Defence. Dubai Municipality's resolution requires Civil Defence conditions to be met for every decoration job, permit or not. The DDA will not issue its completion certificate without the Dubai Civil Defence completion certificate.
  4. DEWA. Only if the scope changes the load or needs new meters. Dubai Municipality issues a free NOC addressed to DEWA for more current or new meters in 2 working days; DEWA's own fit-out connection is applied for by the contractor or consultant.
  5. Completion. The contractor applies for the completion certificate (DDA: estimated 2 working days, no fee listed; Dubai Municipality: through its building completion service). Free-zone landlords also want as-built drawings, test certificates and warranties.

Who approves fit-out in each part of Dubai?

It depends on the jurisdiction the building sits in, not the emirate. Summary from the dataset; the full table with fees, notes and a source per cell is at fit-out approvals by jurisdiction.

JurisdictionApproving bodyPermit, as the body names itWho submitsPublished timing
Dubai Municipality (mainland)Dubai MunicipalitySelf Permit to Carry Out Decorative Works (decoration works permit, units over 100 sq m)Contractor on the Dubai Municipality approved list (building contracting or decor company)Instant (self permit)
Dubai Development Authority (DDA)Dubai Development AuthorityFit-Out PermitFit-out contractor appointed by the tenant2 working days (estimated)
Trakhees (PCFC areas)Trakhees, Civil Engineering Department (Modification & Compliance)Modification PermitConsultant or contractor, online through Trakhees7 working days from payment approval (target)
DMCCDMCC (NOC), then Concordia for the fit-outRequest for NOC to Concordia - Fit-outDMCC company or the property owner (for the NOC)Not published
DIFCDIFC Investments (landlord), under its Fit-Out ManualNot publishedTenant, through the DIFC Client PortalNot published
JAFZAJafza (Modification NOC), Trakhees (modification permit) and Civil Defence for major fit-outModification NOC - Jafza Offices & Retail Units (or Jafza Warehouses)Tenant's fit-out consultant or contractor, through the tenant's Dubai Trade accountModification NOC 3 working days; first review 2 working days
Dubai SouthDubai South (Dubai World Central Corporation)Fit-out Work Permit (with a Fit-out HSEQ NOC)Contractor registered with Dubai South; locally registered consultant for designNot published
Dubai Airport Freezone (DAFZA)Not publishedNot publishedNot publishedNot published
Dubai World Trade Centre (DWTC)DWTC Authority, under its Authority Fit-Out PolicyNot publishedNot publishedNot published
Dubai Silicon Oasis (DSO)Not publishedNot publishedNot publishedNot published
Expo City DubaiNot publishedNot publishedNot publishedNot published

"Not published" means the body's own website or documents did not state it when we checked on 3 November 2026. We do not fill gaps from other zones. Not sure which jurisdiction your building is in? Use which authority approves.

Do small office fit-outs need a permit?

On the mainland and in DDA zones, not if the unit is 100 sq m or less or is inside a shopping mall. The work must still meet Civil Defence conditions, have the owner's written consent and stay inside the unit's boundaries; Dubai Municipality still requires an approved contractor, and the DDA a Dubai-licensed fit-out contractor. In DDA zones, painting, non-structural demolition, like-for-like ceilings, furniture, flooring, low partitions and reinstatement need only the landlord's or facilities manager's NOC or permit to work. Structural changes, a change of use, a mezzanine or merging units need a building modification permit instead.

Who signs and submits the fit-out application?

The contractor, in most places; the tenant appoints them and provides the lease and consent.

StepWho submitsBody
Decoration works permit (units over 100 sq m)Contractor on Dubai Municipality's approved listDubai Municipality
Fit-Out Permit and completion certificateFit-out contractor appointed by the tenantDDA
Modification PermitConsultant or contractor, onlineTrakhees
Modification NOCTenant's fit-out consultant or contractor, through the tenant's Dubai Trade accountJAFZA
NOC to Concordia, fit-outThe DMCC company or the property ownerDMCC
Fit-out drawings and Work PermitTenant's designers for drawings; Dubai South-registered contractor for the permit and government approvalsDubai South

Whoever submits must be properly registered: since 8 January 2026 contractors working anywhere in Dubai, free zones included, must be on the Contractor Register under Law No. 7 of 2025 (what that means); who does what between designer and contractor is in fit-out contractor, interior designer or design-build. The DDA also registers the consultants and contractors who submit in its zones (AED 250 a year, 2 working days).

What documents does a fit-out permit need?

For a DDA Fit-Out Permit: the permit request, the tenant's appointment letter for the contractor, the Ejari, NOCs from the relevant authorities, and approved stamped and proposed drawings. Other bodies ask for similar papers, and free-zone landlords add their own.

  • From you, the tenant: the lease or Ejari, the landlord's NOC or written consent, appointment letters for the designer and contractor, your trade licence, and any fit-out deposit the landlord asks for (Dubai South takes an undated security cheque).
  • From the designer: the fit-out drawing set (layout, ceilings, MEP, fire), stamped where the body requires it, and the programme.
  • From the contractor: trade licence and registration, insurance (Dubai South lists contractor's all risks, public liability and workers' compensation), risk assessment and HSE plan, Civil Defence and DEWA approvals.
  • At completion: the Civil Defence completion certificate, test and commissioning certificates, as-built drawings, operation and maintenance manuals and warranties.

Before you sign a fit-out contract

Write down who applies for each approval and who pays the fees, because quotes often leave it out. Approval fees vary: the DDA charges AED 0.90 per sq ft (minimum AED 200, maximum AED 10,000) plus AED 20; most free zones publish no fee. For what the works themselves cost, see office fit-out cost per sq ft; to line up two or three quotes, use the quote comparison tool. For homes rather than offices, see villa renovation approvals.

Questions

Who approves a fit-out in Dubai?

The landlord first, then the authority for the area: Dubai Municipality on the mainland, the Dubai Development Authority in zones such as Dubai Internet City and Media City, Trakhees in PCFC and Nakheel areas, and the free zone's own process in DMCC, JAFZA, DIFC or Dubai South. Civil Defence and DEWA follow where the works touch fire systems or power.

Do I need a permit for a small office fit-out?

Not from Dubai Municipality or the DDA if the unit is 100 sq m or less, or is in a shopping mall. The works must still meet Civil Defence conditions and have the owner's written consent, and in the DDA a licensed fit-out contractor must do them.

Who applies for the fit-out permit, the tenant or the contractor?

The contractor, in most places. Dubai Municipality takes applications only from a contractor on its approved list, and the DDA names the fit-out contractor as the requester. Trakhees and JAFZA accept the consultant or contractor; in DMCC the company or owner requests the NOC.

How long does fit-out approval take in Dubai?

Published service times: Dubai Municipality's decoration self permit is instant, the DDA Fit-Out Permit is an estimated 2 working days, Trakhees targets 7 working days from payment, and the JAFZA Modification NOC takes 3 working days. Landlord, Civil Defence and DEWA steps come on top.

Do I need Civil Defence approval for a fit-out?

Usually yes. Dubai Municipality requires Civil Defence conditions to be met, the DDA asks for the Dubai Civil Defence completion certificate before its own, JAFZA lists Civil Defence initial approval for major fit-out, and Dubai South names Civil Defence for fire and LPG.

What documents does a fit-out permit need?

For the DDA: the permit request, the tenant's appointment letter for the contractor, the Ejari, NOCs from the relevant authorities, and approved stamped and proposed drawings. Dubai Municipality needs the owner's written consent. Free-zone manuals add insurance, method statements and a deposit.

Keep going

Sources

This guide is general information, not legal advice. Rules change and vary by community and authority: confirm with the authority or your consultant before you start work.

Free for homeowners

Ready to get offers?

You get an email receipt at once, and within 1 working day (replies 08:00–20:00, Mon–Sat) we tell you whether verified businesses are available for your area. Businesses see the job and the area, never your contact details, until you and the business both confirm the same offer.

Step 1 of 3The job
Step 2 of 3Budget and timing
Budget
When do you want to start?
Step 3 of 3How we update you

We confirm your request within 1 working day. Businesses contact you once verified in your area.

Get matched offers

Get offers from fit-out companiesFree · verified businesses · your details stay private