Quality checks by trade
What good work looks like, with the numbers to check, and the moments to see it before it disappears under tiles, plaster or a ceiling. Free, for homeowners and the contractors who work to it.
A renovation in order: the four hold points in coral
The most useful checks in a Dubai renovation happen before work is covered: pressure-test new pipes and photograph walls before they close, see the waterproofing flood test before tiling, check services above a false ceiling before boarding, and tap-test the first tiled room before grouting. Each trade page lists the checks, with the numbers and their basis.
Inside the home
- WaterproofingBathrooms, kitchens, balconies and roofs 2+coats of membrane, the second at right angles to the first24 hminimum before tiling or testing, longer when cool24 hflood test with the water level marked See the checks
- TilingFloor and wall tiles, inside the home 2 mmfloor joints, kept even with spacers3 mmwall joints1:100steady fall to floor drains See the checks
- Gypsum ceilingsFalse ceilings, bulkheads and drywall 450 mmmaximum between ceiling channels in one major system1200 mmmaximum between hangers and primary channels150 / 230mm screw spacing at board ends and in the field See the checks
- Pipes and cablesPlumbing, electrical and AC before walls close 1.5×working pressure, a common water pipe test benchmark0pressure drop on the gauge over the test periodPull wireleft in every conduit for future cables See the checks
- PaintingWalls, ceilings and woodwork, inside and out 1 + 2primer coat, then two topcoats6 hbetween coats at 23 °C for one common emulsionDrysurface: no damp, dust or grease before painting See the checks
- Block walls and plasterNew walls, partitions and plastering 1.5 cmmaximum plaster per coat for one common ready-mix3+ dayskeeping plaster damp, out of sun and wind¼ blockminimum stagger of vertical joints See the checks
- Demolition and protectionStrip-out, protection and debris NOCcommunity approval before any demolitionIsolatedpower and water off in the area, checked safeLicensedconstruction waste transporter, covered loads See the checks
- Apartments in towersBuilding rules, lifts, protection and neighbours 7–14 daystypical wait for the building management NOCDepositrefundable, often AED 2,000 to 5,0005 daysnotice to building management before mobilising See the checks
Outside
- Outdoor tilingTerraces, pool decks, paths and balconies 3–5 mbetween movement joints, plus at edgesFallsaway from the house, to drains or the gardenFull coveradhesive under each tile, outdoor-rated See the checks
- Pergolas and shadesPergolas, gazebos and carport shades NOCcommunity approval before ordering50 mmblinding under each footingPlumbposts checked with a level before final tightening See the checks
- Swimming poolsPrivate villa pools Registerwith Dubai Municipality before construction1.2 mminimum barrier height around the poolSelf-closingand self-latching gate, opening outwards See the checks
Structure
How the standard works
Written from the working method statements of a Dubai design-and-build contractor, then checked against manufacturer data sheets and published guidance. Each check says which.
- Manufacturer A figure from a manufacturer data sheet or system specification. Follow the data sheet for the product on your job.
- Published standard From a published standard or official guidance, named in the sources.
- Good practice How careful contractors work. Not a legal requirement, but worth agreeing before work starts.
Every page is free to read. With a free account you get the full checklist for each trade, to tick on site with notes and photos, and a PDF to send your contractor.
For contractors
Working to these checks, and showing the photos at each hold point, is the simplest way to win a homeowner's trust. Listed businesses get printable inspection forms for every trade, with hold points and sign-off lines, free in their dashboard. List your business.
Questions
What should I inspect during a renovation in Dubai?
Four moments matter most, because each is the last chance to see work before it is covered: new pipes and cables before walls close, waterproofing before tiling (with a flood test), services above a false ceiling before it is boarded, and the first tiled room before grouting.
What is a hold point?
A point in the works where the next step should wait until someone has checked the work so far, for example no tiling until the waterproofing flood test has passed. Agree the hold points with your contractor before work starts.
Is this an official standard?
No. It is SoukLocal’s own standard, written from contractor method statements and checked against manufacturer data sheets and published guidance. Each check says which. It helps you ask the right questions; it does not replace your contractor’s responsibility or an engineer where one is needed.